How do I do bulk updation of critical item levels in BUSY?
To update the bulk updation of item critical level in BUSY then follow the below steps.
Step 1: Click on Administration
Step 2: Then Bulk updation
Step 3: Then Update Item critical levels
Step 4: Select the item for updation either for one item, group of item or all items and required vouchers.
Step 5: Then select the required no. of days to be picked and date range.
Note : Do this process after the data backup.